[HamWAN PSDR] VOTE: Power backup expansion project
Carl Leon
carl at n7kuw.com
Fri Feb 5 16:44:21 PST 2021
Correct, Buck is on generator year round.
-----Original Message-----
From: PSDR <psdr-bounces at hamwan.org> On Behalf Of David C. Jenner via PSDR
Sent: Friday, February 5, 2021 4:42 PM
To: Puget Sound Data Ring <psdr at hamwan.org>; Bart Kus <me at bartk.us>
Subject: Re: [HamWAN PSDR] VOTE: Power backup expansion project
Doesn't Buck Mtn run on generators all the time? With maybe 6 months or more fuel?
73,
Dave
K7DCJ
On 2/5/21 12:41 PM, Bart Kus wrote:
> Hello,
>
> During the recent wind storm event in January, HamWAN lost utility
> power to some sites. This triggered network outages that affected
> users and repeaters that relied on those sites. It was far from our finest hour.
> "When all else fails", HamWAN should not be the first in line. I'd
> like for 2021 to be a year we focus on reliability. Having a reliable
> power system at every site seems like a good place to start that
> journey. In each of the power failures in January, a generator system
> failed to activate. In these cases, we need at least 24 hours to
> mount a response in fixing generators. This means our battery backup
> systems should be sized for at least 24 hours of runtime. I have
> acquired a couple UPSes that can achieve this. They are composed of the main UPS:
>
> https://www.apc.com/shop/us/en/products/APC-Smart-UPS-XL-Modular-3000V
> A-120V-Rackmount-Tower/P-SUM3000RMXL2U
>
> And one external (and chainable!) battery expansion module:
>
> https://www.apc.com/shop/us/en/products/APC-Smart-UPS-XL-Modular-48V-E
> xtended-Run-Battery-Pack/P-SUM48RMXLBP2U
>
> They also feature an AP9631 network interface module in each UPS, so
> we can monitor and control the power system. As you can see, each UPS
> costs about $3600 new, so the two I acquired would be $7,200 new.
> However, I managed to find used units and purchased brand new
> batteries for them. *The total cost for these two systems is $963.71.*
> One of them is deployed at Rattlesnake ("Snoqualmie shack") already:
>
> https://photos.app.goo.gl/HTomAzJUnrjuJ3bw8
>
> If we ever want to expand the battery capacity of these, we can simply
> plug in more battery modules.
>
> I'm hoping to deploy the 2nd system in the other building on
> Rattlesnake ("DNR shack"), but that hasn't happened yet.
>
> --Bart
>
>
> _______________________________________________
> PSDR mailing list
> PSDR at hamwan.org
> http://mail.hamwan.net/mailman/listinfo/psdr
>
_______________________________________________
PSDR mailing list
PSDR at hamwan.org
http://mail.hamwan.net/mailman/listinfo/psdr
More information about the PSDR
mailing list